KR220M Singapore mixing pile construction

  • Categories:Case
  • Time of issue:2021-08-05 09:38

(Summary description)The multifunctional rotary drilling rig KR220M customized by Jiangsu TYSIM Machinery for customers was unveiled in Singapore. Our company dispatched after-sales service personnel to guide the installation and commissioning work, train the operators, and achieve one-stop service, which has won praise from customers.

KR220M Singapore mixing pile construction

(Summary description)The multifunctional rotary drilling rig KR220M customized by Jiangsu TYSIM Machinery for customers was unveiled in Singapore. Our company dispatched after-sales service personnel to guide the installation and commissioning work, train the operators, and achieve one-stop service, which has won praise from customers.

  • Categories:Case
  • Time of issue:2021-08-05 09:38
  • Views:
Information
TYSIM Machinery KR220M Long Spiral Construction Parameters
 
Spinner type: KR220M Large drilling depth: 20m
 
Large drilling diameter: 800mm Output torque: 220kN.m
 
The multifunctional rotary drilling rig KR220M customized by Jiangsu TYSIM Machinery for customers was unveiled in Singapore. Our company dispatched after-sales service personnel to guide the installation and commissioning work, train the operators, and achieve one-stop service, which has won praise from customers.

 

A

 

TYSIM after-sales service personnel guide the construction on site
 
This project is a leisure plaza near the subway in Singapore. Our company’s KR220M is equipped with a multifunctional mast and a single-shaft mixing device is mounted for construction. The mixing pile has a diameter of 1200 and a mixing depth of 12 meters. It is expected that the single pile is poured and mixed cement slurry 7-8 square.
 
Construction essentials:
 
1. Pour clean water while drilling down to the required depth.
 
2. The cement slurry is lifted while rotating forward, and the lifting speed is controlled at 0.8-1m/min to ensure sufficient mixing.
 
3. The cement slurry is poured down to the required depth while rotating forward again, and the speed is controlled at 0.8-1m/min.
 
4. While grouting the cement slurry while rotating, the speed is controlled at 0.8-1m/min, and the hole is finished.
 
5. Pour clean water to clean the pipeline.
 
According to the above process, the construction of a single pile takes 50-60 minutes, and 6-7 piles can be completed every day, which meets the requirements of the construction period.

 

A

KR220M Rotary Drilling Rig Construction Picture

 

A

KR220M Rotary Drilling Rig Construction Picture

 

A

KR220M Rotary Drilling Rig Construction Picture

 

The construction of the project has been completed a few days ago, and the construction requirements have been met from the verticality of the pile to the water retaining effect. This fully verifies the feasibility of the KR220M multi-function rotary drilling rig for single-shaft mixing construction, and also lays the foundation for our equipment in the Singapore market.

 

A

Construction completed and excavation

 

Scan the QR code to read on your phone

Related Products
Ten years of focusing on small and medium-sized piling machinery
CopyRight © 2021 Tysim Piling Equipment Co., Ltd All rights reserved.    苏ICP备13058972号   Powered by:www.300.cn   IPv6 network supported
TOP

TYSIM